Isolate the agreed duct section, seal its intentional openings, apply the specified positive or negative pressure with suitable test equipment, and measure the airflow needed to maintain that pressure. Compare the result with the project’s stated acceptance method and retain the boundary drawing, instrument details and conditions.
That is a different job from measuring the operating fan’s airflow. A leakage rig measures losses through a defined test envelope. Commissioning checks how the installed fan and air path perform in operation. Passing one does not prove the other.
Start by asking what decision the test must support: acceptance of new ductwork, investigation of a suspect section, or verification after a repair. That decision determines the scope and the evidence required. Do not choose a convenient pressure first and invent the acceptance rule afterward.
Engineering scope and sources reviewed 2026-10-17 · Project conditions still govern final selection