Match the delivery to its shipping documents, check the packaging and accessible equipment for damage, record discrepancies at handover, and keep unresolved items out of the installation release. Preserve photographs, identification and packaging evidence, then notify the carrier and supplier through the agreed process.
Do not use the full purchase order as the only receiving list. Fans, guards, shutters, controllers and loose hardware may arrive in separate consignments. An item absent from today’s crate may be missing, shipped separately or excluded from the order; those are three different problems.
Assign one person to own the receiving record. When several people photograph the same damage but nobody links the images to a packing-list line, the supplier still has to ask the basic questions again.
Engineering scope and sources reviewed 2026-10-17 · Project conditions still govern final selection